The Hongkong Electric Co Ltd (HEC) is committed to
providing a high quality power supply to its customers with due care for the environment. Recognizing the importance of
sustainable development, HEC is proposing to install a wind turbine of capacity
ranging from 600 to 850kW as a demonstration project of the utilization of wind
energy for renewable power generation on Lamma Island, Hong Kong.
Following the completion of a 12-month wind power
monitoring exercise on Lamma Island in November 2002, a wind atlas was
developed to assess the wind potential of the Island. A number of areas were identified as having wind power
density over 150W/m2, equivalent to
the average wind speed of about 5.5m/s, and generally considered suitable for
wind energy utilization. The
existing power supply to Lamma Island is by means of 11kV power lines,
transformer pillars and low voltage distribution cables from the Lamma Power Station.
Following the completion of a site selection
exercise Tai Ling Tsuen was chosen as the optimum location for the wind turbine
(Figure 1.1). The output will be connected to the
existing power grid for supplying renewable energy to HEC customers.
The Project is classified as a
Designated Project by virtue of Item D.1 of Part I of Schedule 2 under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO).
The main objective of this Environmental Impact Assessment
(EIA) study is to provide information on the nature and extent of potential
environmental impacts arising from the construction and operation of the
proposed Project and related activities taking place concurrently. The study will also contribute to
decisions on the overall environmental acceptability of the Project, after the
implementation of environmental mitigation measures.
The EIA provides a detailed assessment of the potential
environmental impacts associated with the Project, in relation to the issues
specified in the EIA Study Brief (No.
ESB-112/2004), including noise, ecology, landscape and visual, air quality and
water quality.
HEC
is proposing to install a 600-850kW wind turbine as a demonstration of the
potential for wind utilization in generating power. The wind turbine will be built in a grid connection scheme
for supplying “green” electricity to HEC
customers. The
objectives of the project are as follows:
·
Demonstration of
utilizing wind energy for power generation: The
proposed wind turbine will
be the first utility scale and grid-connected wind project in Hong Kong. Based on the wind potential on Lamma, the
proposed wind turbine will harvest about 700MWh of electricity per annum, helping to avoid the use
of up to 240 tonnes of coal and reduce
the associated emissions every year.
·
Education purpose: Visitors’
facilities such as display boards and guided tour will be provided at the wind turbine site to
explain the principle of power generation by wind and the benefits of renewable
energy. The wind turbine project
will serve as educational use for promotion of green awareness among the
public, in particular with students.
·
Wider application of
renewable energy: The project will provide invaluable local experience on the design, construction, operation
and maintenance of wind turbines. Future utilization of wind energy in Hong Kong can
be explored based on the information collected and experience gained, keeping pace with Government's
policy, and the publics expectation of the promotion of renewable energy and improvement in air quality.
The Project is the construction and operation of a 600-850
kW wind turbine and associated equipment at Tai Ling Tsuen on Lamma
Island. The output will
be connected to the existing power grid for supplying renewable energy to HEC
customers. The
operation of the wind turbine will be monitored and controlled through a
central monitoring system located in a control room of the Lamma Power
Station. The wind turbine site
will be unmanned and will only require attendance of operational personnel
during emergency or routine maintenance.
The proposed wind turbine is a “horizontal axis”
machine which consists of three rotor blades turning around a horizontal
hub. The hub is connected to a
gearbox and a generator which are located inside a nacelle. The nacelle houses the mechanical and
electrical components and is mounted on the top of a tubular tower. A transformer will be installed at the bottom of the wind turbine
tower. Switchgear and power
conditioning devices will be housed inside a high voltage distribution pillar
(HVDP) made of stainless steel (4.6m L x 2.5m W x 2.8 m H) installed within the
site boundary of wind turbine.
Power cables will be buried underground for connecting the wind turbine,
HVDP and the nearby 11kV power grid on the 275kV cable route. The output from the wind turbine is thereby
transmitted to the existing power grid.
The synchronous generators of the grid system supply magnetizing current
for the induction generator of the wind turbine. An Auto-synchronous Controller will be required to control
the operation of a Synchronizing Breaker with respect to the wind turbine
output voltage and frequency.
The facilities required at the wind
turbine site are as described in Section 2.2. Most of the equipment will be delivered to the site via the existing 275kV Cable Route. The
wind turbine site (Project Area) covers an area of about 4,400 m2 and is situated
adjacent to the existing 275kV cable road. All the
construction activities will be restricted within the Project Area. A
flat area for siting the wind turbine, the associated electrical equipment and
access platform will be formed by cutting back the hill slope. The site platform will be formed by
excavation with minor retaining wall constructed around the perimeter of the
site. A circular concrete footing will
be constructed for supporting the wind turbine. The construction
work on site is minimal and will not result in adverse impacts to the
environment.
The main activities and construction
sequence are:
·
Excavate the site by cutting and
filling to form a site platform (affected area is approximately 3,100 m2
and excavated materials is approximately 1,300 m3);
·
Construct retaining wall around site
perimeter;
·
Backfill and level site (nearly 95% of the excavated materials could be used
for backfilling, the remaining
materials will be transported by trucks to the HEC Power Station for offsite
disposal);
·
Construct circular concrete footing for
wind turbine foundation;
·
Reinstate ground;
·
Erect wind turbine using one heavy duty
mobile crane and one light duty mobile crane, and high voltage distribution
pillar;
·
Lay cables;
·
Landscaping works including planting of
trees and shrubs.
The
wind turbine will be designed for fully automatic start up, synchronization to
the 11kV power grid, power regulation, disconnection from the grid and shut
down. It will produce electricity
when the wind speeds are in the range of 2.5 to 25 m/s. The rotor blade will rotate from 14 to
31 rpm approximately under normal circumstances. The wind turbine will cut-off from the grid when wind speeds
are below 2.5 m/s or above 25 m/s.
The
operation of the wind turbine will be monitored and controlled through a
central monitoring system located in a control room of the Lamma Power
Station. The wind turbine site
will be unmanned and require attendance of operational personnel only during
emergency or routine maintenance.
The construction of the Project is
scheduled to commence in the first quarter of 2005 and will be
completed within about 12 months, 8 months for civil works including site preparation and foundation, and
4 months for electrical and
mechanical works (such as installation & erection of the
wind turbine).
Desktop screening and site surveys were
conducted to identify potential sites for a wind turbine of suitable size on
Lamma and Po Toi Island and were based on the criteria recommended in the
guidelines for wind energy development issued by reputable international
organizations of wind energy. The
site search was confined to Lamma and Po Toi where reliable wind data are
available and locations away from the densely populated area.
Po Toi Island is an
ecologically sensitive area which has
been identified as a potential Country Park. In view of the accessibility considerations and absence of a
power grid, Po Toi is considered neither technically feasible nor
environmentally and economically attractive for a demonstration project with
commercial scale wind turbine.
Once the above considerations had been accounted
for, site selection was focussed on Lamma Island. The wind turbine site was then examined against engineering requirements and environmental concerns and further refined using the following site screening criteria:
·
Wind potential;
·
Site access;
·
Height restriction;
·
Electrical
connection; and
·
Area and land-use
Taking
into account the above criteria, six potential sites were identified with the application of constraint mapping
techniques (Figure 2.1). The six long-listed sites are:
Site 1 - Lamma Power
Station Extension
Site 2 - Tai Ling
Site 3 - Yung Shue Long
Site 4 - Tai Peng
Site 5 - Pak Kok Tsui
Site 6 - Lamma Quarry
All of the sites avoided
ecologically sensitive areas, SSSI and the potential Country Park at South
Lamma. The six identified sites are situated along the existing 275 kV Cable Routes which are the only vehicular
roads on Lamma island.
|
Figure 2.1 Long-listed
Sites for Wind Turbine Installation
Having identified sites that meet the broad
environmental and engineering criteria, a site-specific appraisal has been
conducted to establish a short-list of feasible sites for further detailed
investigation.
Qualitative approaches have been adopted to identify
potential conflicts with the development of the wind turbine. Each potential
site was scrutinized more closely
with engineering criteria on wind potential, geological considerations and
electrical connection; and environmental criteria concerning visual, noise and
ecological impacts. Of the 6
long-listed sites within the areas of least constraints, four sites have been
excluded due to principal conflicts identified, leaving the following two sites for
the final comparative assessment:
Site 2 -
Tai Ling
Site 4 -
Tai Peng
The two sites have been evaluated
and compared according to the potential impacts likely to arise as a sequence
of construction and operation of the wind turbine system. Site 2 – Tai Ling is identified as the overall
preferred site due to its distinct merits in site access, ground conditions,
noise and visual impact compared with Site 4 – Tai Peng. The site at Tai Ling is also the more
remote of the two in terms of proximity to village houses.
The preferred site at Tai
Ling is a relatively level platform to the west of the joint bay of HEC's
existing cable route. Taking
advantage of the joint bay area as part of the works area for erection of the
wind turbine, the landtake requirement can be optimized. Moving the wind turbine site further
north away from the noise sensitive receivers are not preferred due to the need
for extensive excavation of the hill slope to form access road for the wind
turbine.
The planned capacity of the wind turbine
at Tai Ling is 600 to 850 kW depending on the model sizes
available from respective suppliers.
The wind turbine capacity is
selected based on the following considerations:
·
600 kW class wind turbine is of
proven design with a large number of installations worldwide.
·
600 kW class wind turbine is
now becoming the smallest size available from the majority of the suppliers due
to the worldwide trend for large capacity machines.
·
600 kW class wind turbine is the
maximum size of machine complying with the height restriction at Tai Ling
Site.
On the other hand, the wind turbine is beneficial to
the environment over the traditional coal-fired or gas-fired plant as it helps
to reduce the air pollutant and greenhouse gas emissions. Assuming a 600 kW wind turbine producing electricity of 700 MWh/yr, the
emission reduction of major air pollutants compared with that of the same
capacity at the existing coal-fired plant is presented in Table 2.1.
Table 2.1 Air
Pollutant Emission Reduction by Wind Turbine (a) (b)
Air Pollutants |
Annual Emission Reduced (kg) |
Sulphur dioxide (SO2) |
1941 |
Nitrogen oxides (NOx) |
1008 |
Particulates |
100 |
Carbon dioxide (CO2) |
605.5 tonnes/yr (i.e., 605,500 kg/yr) |
Note: (a)
Assuming 600 kW
wind turbine produce electricity of 700 MWh/yr. (b)
Based on
average emission generated from the existing coal-fired units including of
2.773 kg/MWhr of SO2, 1.44 kg/MWhr of NOx, 0.143
kg/MWhr of TSP and 865 kg/MWhr CO2 |
It can be seen from above table that the operation of the wind turbine
can bring about benefits through the reduction in emissions of air pollutants
such as SO2, NOx, CO2 and particulates.
The nature and extent of the environmental impacts
associated with the construction and operation phases of the Project are
summarised below. Specific
mitigation measures for the Project, as well as environmental monitoring and
auditing procedures, have been developed during this EIA. The Implementation Schedule of the
recommended measures is presented in Annex D of the EIA Report.
Unmitigated construction activities associated with the Project will not cause adverse noise impact to the nearby NSRs with the predicted construction noise levels in the range of 46 – 61 dB(A), which comply with the stipulated noise criterion. The mitigation measure of adopting good site practices is proposed to further minimise the construction noise impact to the environment. Regular site audits will be conducted during construction to ensure the plant inventory used on site is consistent with the assumptions in the EIA report.
With the adoption of a
maximum sound power level of 100 dB(A) and a pure tone free wind turbine , the
predicted facade noise levels will comply with the night-time noise criterion
at all NSRs. It is proposed that
the allowable maximum sound power level of 100 dB(A) with no pure tones shall
be included in the tender specification of wind turbine. The supplier shall
guarantee this noise level by providing certificate of measurement and verify
the overall noise level during commissioning and testing in accordance to
international standard procedures such as IEC 61400-11. Whenever necessary, the supplier shall
apply attenuation measures to achieve the guaranteed noise level. There has been
information from the suppliers that the 100 dB(A) and pure tone free wind
turbine of 600-850 kW range is available and practicable. Noise
monitoring during the operational phase is recommended to be carried out during the night-time period at the agreed
monitoring location once every fourteen days for a period of six consecutive
months so as to ensure the compliance with the stipulated noise
criterion at the nearby NSRs.
The ecological resources recorded within the
Study Area included secondary woodland, shrubland, shrubby grassland, stream
and village/ developed areas, as well as associated wildlife. Of these habitats, secondary woodland
(at least 200 m from the wind turbine) and the middle course of a stream near
to Lo Tik Wan (Stream S4, approximately 500 m from the wind turbine) have
moderate to high and high ecological value respectively. The remaining habitats are of low or
low to moderate ecological value.
A total of 14 species of conservation interest were recorded within the
Study Area, including five bird species (Black Kite, Greater Coucal, Lesser Coucal,
Emerald Dove and White-bellied
Sea Eagle),
eight uncommon butterfly species (Red Lacewing,
Bush Hopper, Common Duffer, White-edged Blue Baron, Tree Flitter,
Yellow Orange Tip, Swallowtail and Small Cabbage White) and one
amphibian (Romer’s
Tree Frog). Three calling male Romer’s Tree Frog were recorded within and
adjacent to the Project Area during the surveys. A total of 17 bird species were observed during the vantage
point surveys, with a total of 1,290 flight attempts in the Study Area. The flight attempts of most of the
recorded species were generally flying < 10 m above the ground level near
the Project Area. Only Black Kite
(144 attempts, the maximum number of individuals recorded was 23 during the
surveys), Barn Swallow (3 attempts) and Little Swift (2 attempts) were recorded
flying over and crossing the location of the proposed wind turbine at a height
> 10 m and <100 m above the ground level during the surveys.
In conclusion, the direct ecological impact due
to the construction of the wind turbine is expected to be low, and will not
contribute to any potential cumulative impact. In view of the generally poor vegetation cover and the
dryness of the upland areas, it is believed that the Project Area and areas in
the vicinity do not provide optimal habitats for the Romer’s Tree Frog.
The impacts on the Romer’s Tree Frog are expected to be low given that
pre-construction translocation of Romer’s Tree Frogs (adult and tadpoles, if
any) present at the site will be conducted.
Bird collisions
are the main concern of the operational impacts of any wind turbine
development. Barn Swallow, Little Swift and Black Kite, recorded as
utilising the Project Area in this study, are the confirmed potential species that may be
affected by the wind turbine during operation. Site selection is crucial to minimizing wind turbine bird
collision. Since the wind turbine site is not considered to
be either within important bird habitat or on the flight path of migratory
birds, the impacts due to bird collision are of low magnitude and therefore not
considered to be unacceptable.
No adverse residual impact is expected after the
implementation of the recommended mitigation measures. One year bird monitoring will be undertaken to
demonstrate that the wind turbine is having low magnitude of and not having an
unacceptable impact on bird species.
The whole Study
Area is considered to be covered under one single Landscape Character Area, LCA
1 - North Lamma Coastal Uplands.
Landscape Resources found within the Study Area include LR1 - secondary
woodland, LR2 - shrubland, LR3 - shrubby grassland, LR4 - streams and LR5
-village/developed area.
The Project
would result in the disturbance of only LCA1 and LR3 involving approximately
3,100 m2 out of which approximately 1,400 m2 will be reinstated. Resulting in a net loss of 1,700 sq.m.
.
Specific
mitigation measures have been proposed to minimize identified impacts,
including reinstatement of disturbed areas, compensatory planting, colour
scheme, soil conservation and selection of low rotating speed machine.
With the
implementation of the mitigation measures proposed, the magnitude of change to
LCA1 and LR3 are small. The
residual impact significance threshold of LCA1 is moderate/ adverse for both
years 1 & 10. Appropriate landscape planting including trees, shrubs and
grasses will result in a net increase in the quantity of vegetation at the
Project Site resulting in a significance threshold of the residual impact for
LR3 to “slight/adverse” during Year 1 of operation and “slight/beneficial”
during Year 10 of operation.
Visually, the
proposed wind turbine would result in slight to moderate/ adverse residual
visual impact on views from Lamma Island and Hong Kong Island during operation
except for the case of viewers from Tai Ling Pavilion and the cable route
adjacent to the site where the significance threshold would be significant.
With the gain in knowledge of the benefits of renewable energy such as the
improvement of air quality, the likelihood of acceptance of the visual impact
would be increased.
The overall
residual impacts on landscape and visual aspects are considered to be
acceptable with mitigation measures.
Dust nuisance is the only potential
air quality impact during the construction of the Project. Site formation, foundation
construction, cable laying, wind turbine erection and landscaping works are the
main construction activities. Wind
erosion, materials handling, on-site stockpiling and vehicle movements are the
main dusty activities. Since the
site area is small, construction period is short with minimal construction
activities and the distance from the ASRs is more than 185 m away, therefore,
with the implementation of dust suppression measures, the potential for causing
dust impact is very low. However,
to protect the ASRs, regular site auditing is recommended to ensure the recommended mitigation measures are properly
implemented.
No air quality impact would be
envisaged during the operation of the wind turbine. The wind turbine will displace emissions of greenhouse gases
and other emissions from conventional power generating plant. Estimates of the potential emission
reductions have been presented in the Table 2.1.
During
the construction phase it was determined that minor impacts to water quality
could arise directly from land-based construction works. These works relate to excavation and
construction of the foundation for the wind turbine, and underground cable
laying. No direct construction
runoff is expected. However,
stormwater runoff from the construction site could occur during
rainstorms. Mitigation measures
were described, which would provide a series of good site management practices
to minimise the impact of stormwater runoff.
No
operational impacts to water quality are expected to occur. No mitigation measures are therefore
necessary. Based on the impact
assessment, no EM&A measures are required. The mitigation measures specified as well as good site
management skills are considered sufficient to prevent impacts occurring.
During construction of the Project, environmental
monitoring will be necessary to assess the effectiveness of measures
implemented to mitigate potential environmental impacts. Regular site auditing is also
recommended to ensure that potential impacts from other sources are adequately
addressed through the implementation of the mitigation measures defined in this
EIA Report.
During operation of the Project, the monitoring work is
focussed on ecology, specifically operation phase impacts to birds and to a
noise sensitive receiver. Details
are presented in the EM&A Manual.
The EIA has critically assessed the overall acceptability
of any environmental impacts likely to arise as a result of the construction
and operation of the wind turbine on Lamma Island. Where necessary and practicable, the EIA has specified the
conditions and requirements for the detailed design, construction and operation
of the Project in order to mitigate environmental impacts to acceptable levels.
This EIA Study has predicted that the Project will comply
with all environmental standards and legislation after the mitigation measures
are implemented. The EIA has thus
demonstrated the acceptability of any residual impacts from the Project and the
protection of the population and environmentally sensitive resources. Where appropriate, EM&A mechanisms
have been recommended during construction and operation to verify the accuracy
of the EIA predictions and the effectiveness of recommended mitigation
measures.
The study concluded that there
would be no adverse long term or cumulative effects/impacts on the environment.
In conclusion, it is considered that the EIA provides a suitable basis for the
Director of Environmental Protection to consider granting the Environmental
Permit to allow the construction and operation of the Project.